On every visit: measured, photographed and tested, before anything is covered up.
We check, you see, you decide.
Three things happen every week of your build. Here's each one, then the five steps from your first call to handover, and the dashboard where it all lands.
Three things happen every week.
Tap a scene to play it again. Your money and your instructions go straight to your contractor. Vakeel is copied, never in between.
What to pay, what to hold and what to decide, with the photos and tests behind it.
Your yes and your money go straight to your contractor. Vakeel is copied, never in between.
What Vakeel never does: hold or move your money instruct your contractor on our own account recommend anyone take a fee from anyone but you
From your first call to handover, in five steps.
You can start at any step. Most owners start free, with their quotes side by side.
Put your quotes side by side, or tell us where your project is today.
1, 2 or 3 a week, for a fixed monthly fee set when you sign.
Every visit checked, measured and photographed. Before anything is covered, we look.
Every bill gets our position: pay this, hold that, and why.
Every check, photo and test kept, for your defects claims and for a buyer.
What the contractor claims. What we verified. What you paid.
Three numbers on one line, updated after every visit. As long as what you've paid stays below what we've verified, you're never ahead of the work.
Paid is below verified. You're not ahead of the work.
On the latest bill for the sample villa: pay AED 656,500, hold AED 123,500 until Tuesday's pipe test. You pay your contractor yourself.
See your build from anywhere, with the evidence.
A sample villa in Jumeirah Islands, with sample data. Choose Simple or Advanced, and pick a screen.
+14 days135 days to go
Planned 52% · verified 47% · paid 39%
Decide: master-bath tileSupplier cut-off
YouSite visit: pipe test, bath 29am, we attend
Payment 4: AED 123,500 heldUntil both tests pass
Held- Paid2.41M
- Due657k
- Held124k
- To build2.97M
Keep the specified tile
AED 0Change the tile We recommend
20,150After the screed it costs about 45,500.
LiveCAM 120 SEP 2026 · 10:42:07Second plaster gang started, north wall
14 people signed in
Bath 2 upstand rework started
Master-bath tile samples on site
- Paid2,405,000
- Verified, due656,500
- Held123,500
- Still to build2,965,950
Held until Tuesday's pressure test and the bath 2 flood test.
MEP first fix, ground floorLiving and bath 2 runs untested
188,50084,500Waterproofing, baths 2 and 3Bath 2 upstand too low
110,50091,000The specified tile was discontinued. Two options are on site as samples.
Keep the specified tile
AED 0Change to your selected tile We recommend
20,150+4 daysSame result at no cost, instead of variation V-05 at AED 11,050.
Before the scaffold comes down.
Laundry drainage moved
Agreed 52,000Two-coat waterproofing
Agreed 59,150Monthly site cleaning
Rejected 32,500+14 days135 days to go
Original 3 Feb 2027. A second plaster gang from 28 Sep aims to win back 5 days.
Pipe test and bath 2 re-check
Master-bath tiling, once the tile is decided
Ground-floor screeds, behind the flood test
Roof waterproofing, behind parapet render
The villa is sound and your money is protected, but the job is two weeks behind and one bathroom must be redone before tiling.
23 checks on this visit · 21 passed · 2 failed
1:04Week 15 walk-throughOne minute, six stopsConcrete, MEP first fix, windows, the ceiling before it closes, waterproofing, and our verdict.Plaster inspected, inside the recovery plan
Slab moisture 3.1%, screeds cleared
Blockwork measured, matches the claim to 0.4%
CAM 1 liveUptime 99.8%20 SEP 2026 · 10:42:07Material trolley through the entranceCAM 1 · access
Movement at the bath 2 workfaceCAM 3 · motion
Delivery at the gate, 6 minutesCAM 1 · access
CAM 2 offline 40 minutes, power isolatedCAM 2 · signal
Ceiling AED 6,337,500
MEP first fix, ground floorLiving and bath 2 runs untested
188,50084,500Waterproofing, baths 2 and 3Bath 2 upstand too low
110,50091,000| Claimed | Verified | Conf. | ||
|---|---|---|---|---|
| PA-1 | 601,250 | 601,250 | 100% | paid |
| PA-2 | 780,000 | 780,000 | 100% | paid |
| PA-3 | 1,023,750 | 1,023,750 | 100% | paid |
| PA-4 | 780,000 | 656,500 | 94% | open |
| PA-5 | 871,000 | 695,500 | 81% | forecast |
Ground-floor screeds, behind the flood test
Roof waterproofing, behind parapet render
Pipe test and bath 2 re-check
Master-bath tiling, once the tile is decided
A second plaster gang from 28 Sep aims to win back 5 of the 14 days.
The villa is sound and your money is protected, but the job is two weeks behind and one bathroom must be redone before tiling.
+14 days135 days to go
Planned 52% · verified 47% · paid 39%
Decide: master-bath tileSupplier cut-off
YouSite visit: pipe test, bath 29am, we attend
Payment 4: AED 123,500 heldUntil both tests pass
Held- Paid2.41M
- Due657k
- Held124k
- To build2.97M
Keep the specified tile
AED 0Change the tile We recommend
20,150After the screed it costs about 45,500.
LiveCAM 120 SEP 2026 · 10:42:07Second plaster gang started, north wall
14 people signed in
Bath 2 upstand rework started
Master-bath tile samples on site
- Paid2,405,000
- Verified, due656,500
- Held123,500
- Still to build2,965,950
Held until Tuesday's pressure test and the bath 2 flood test.
MEP first fix, ground floorLiving and bath 2 runs untested
188,50084,500Waterproofing, baths 2 and 3Bath 2 upstand too low
110,50091,000The specified tile was discontinued. Two options are on site as samples.
Keep the specified tile
AED 0Change to your selected tile We recommend
20,150+4 daysSame result at no cost, instead of variation V-05 at AED 11,050.
Before the scaffold comes down.
Laundry drainage moved
Agreed 52,000Two-coat waterproofing
Agreed 59,150Monthly site cleaning
Rejected 32,500+14 days135 days to go
Original 3 Feb 2027. A second plaster gang from 28 Sep aims to win back 5 days.
Pipe test and bath 2 re-check
Master-bath tiling, once the tile is decided
Ground-floor screeds, behind the flood test
Roof waterproofing, behind parapet render
The villa is sound and your money is protected, but the job is two weeks behind and one bathroom must be redone before tiling.
23 checks on this visit · 21 passed · 2 failed
1:04Week 15 walk-throughOne minute, six stopsConcrete, MEP first fix, windows, the ceiling before it closes, waterproofing, and our verdict.Plaster inspected, inside the recovery plan
Slab moisture 3.1%, screeds cleared
Blockwork measured, matches the claim to 0.4%
Protected, with attention needed
Eight-week trend · 61 → 69
CAM 1 liveUptime 99.8%20 SEP 2026 · 10:42:07Material trolley through the entranceCAM 1 · access
Movement at the bath 2 workfaceCAM 3 · motion
Delivery at the gate, 6 minutesCAM 1 · access
CAM 2 offline 40 minutes, power isolatedCAM 2 · signal
Ceiling AED 6,337,500
| Claimed | Verified | Conf. | ||
|---|---|---|---|---|
| PA-1 | 601,250 | 601,250 | 100% | paid |
| PA-2 | 780,000 | 780,000 | 100% | paid |
| PA-3 | 1,023,750 | 1,023,750 | 100% | paid |
| PA-4 | 780,000 | 656,500 | 94% | open |
| PA-5 | 871,000 | 695,500 | 81% | forecast |
Ground-floor screeds, behind the flood test
Roof waterproofing, behind parapet render
Use the menu inside the screen, and tap the cameras and photos. A preview of a sample villa.
Sign-in needed. Ask us for access on a free call.
One villa, built two ways.
The same villa, once without Vakeel and once with.
Press play and watch both builds month by month: what gets paid ahead of the work, what gets covered up, and when you find out it's late.